Lee East End is growing.
Lee Montessori moved into 2345 R Street SE in the fall of 2020. Our East End campus at that time was only four classrooms, but we knew we were growing, and our eventual goal was to serve grades PK3 - 6th. To meet this goal, and provide free, public, high-quality Montessori education to as many students as possible, we knew we would have to expand our building. Throughout 2021 and 2022, school leadership held community meetings, worked with city officials, and selected an Architect and Contractor to help us achieve our vision of expanding our campus. After numerous road bumps, we were finally able to start construction in July 2023. On August 26, 2024, we welcomed our students and families into our new Elementary Expansion wing!
Click through the pictures below to follow the journey of construction.

Excavation

Tiebacks

Tiebacks

Tiebacks

Excavation and micropiles

Micropiles

Micropiles (October)

Drilling some micropiles

Prep for slab pour (November)

rebar for foundation

Elevator foundation (December)

Foundation walls

Foundation walls and elevator pit (January)

Foundation walls (January)

Geofoam installation (February)

Geofoam installation (February)

Inside the new building; SW corner looking NE; ground level (early April 2024)

Ground level, NW corner looking SE (early April 2024)

Steel installation (April 2 2024)

Steel getting installed! Work on the second floor foundation (late March 2024)

Site work, pre floor pours (April 18 2024)

Floor pours (April 23 2024)

South side exterior framing (April 30 2024)

SE entrance, looking NW (April 30 2024)

Interior staircase installation (April 30 2024)

Interior staircase installation (April 30 2024)

View from Ridge Pl SE, facing NW (April 30 2024)

Interior framing install (May 7 2024)

Looking East from Ground level (May 7 2024)

View from Ridge Place (May 7 2024), framing install in progress.

2nd Floor classroom ductwork (May 14 2024)

View from 2nd floor hallway towards existing building (May 14 2024)

2nd floor hallway, looking West (May 14 2024)

1st floor classroom framing, May 28 2024

1st floor classroom framing, May 28 2024

1st floor hallway looking west, May 28 2024

Exterior view from SE corner of Ridge Place, May 28 2024

Ridge Place entrance - June 4 2024

Future art classroom, first floor - June 4 2024

First Floor classroom, looking over Ridge; showing window frame - June 4 2024

Future library, first floor, looking over Ridge Pl - June 4 2024

North side masonry install, 7/9/2024

1st floor classroom finishes, 7/9/2024

South side exterior, taking down the scaffold. 7/10/2024

Second floor classroom tile, 7/22/2024

Bioponds on south side, along Ridge Place; view from room 7/22/2024

Roof view, pre-dirt; 7/22/2024

Exterior stair installation, 7/22/2024

North side masonry installation, 7/22/2024

Existing building interior demo, 7/22/2024

Ground floor hallway view, 7/22/2024

Future network office, second floor; 7/22/2024

Retaining wall, 8/6/2024

Ridge Place sidewalk, view looking south from stair, 8/12/2024